What is a design consideration when using existing PCIe I/O drawers in a maximum bandwidth/throughput configuration on a new Power 750 system?()A、The new system requires 1 installed processor card for the GX++ bus adapterB、The new system requires a minimu

题目

What is a design consideration when using existing PCIe I/O drawers in a maximum bandwidth/throughput configuration on a new Power 750 system?()

  • A、The new system requires 1 installed processor card for the GX++ bus adapter
  • B、The new system requires a minimum of 2 installed processor cards for the GX++ bus adapter
  • C、The new system requires a minimum of 3 installed processor cards and the HPC InfiniBand cluster adapter
  • D、The new system requires 1 installed processor card for the GX++ bus adapter and the HPC InfiniBand  cluster adapter

相似考题
更多“What is a design consideration when using existing PCIe I/O drawers in a maximum bandwidth/throughput configuration on a new Power 750 system?()A、The new system requires 1 installed processor card for the GX++ bus adapterB、The new system requires a minimu”相关问题
  • 第1题:

    A customer would like to buy a new Power 750 and attach 2 PCIe I/O drawers. What is the minimum configuration which will support this?()

    • A、One processor card and one GX+ expansion card
    • B、Two processor cards and one GX++ expansion card
    • C、One processor card, one GX+ expansion card, and one GX++ expansion card
    • D、Two processor cards, one GX+ expansion card, and one GX++ expansion card

    正确答案:C

  • 第2题:

    A customer wants to migrate their existing cluster onto new POWER6 hardware, and in addition requires thecluster to be migrated from PowerHA version 5.3 to 5.5. Given that AIX 6.1 and PowerHA 5.5 filesets arealready installed in the new hardware, which of the following methods would allow the customer to maintaintheir current cluster configuration?()

    • A、Add the new nodes to the existing cluster, and perform a rolling migration and remove the original nodesfrom the cluster
    • B、Add the new nodes to the existing cluster, and perform a non-disruptive upgrade and remove the originalnodes from the cluster.
    • C、Create a snapshot of the existing cluster and apply the snapshot to the new cluster. Start cluster serviceson the new cluster and stop the original cluster
    • D、Create a snapshot of the existing cluster and apply the snapshot to the new cluster. Stop cluster serviceson the original cluster and start on the new cluster

    正确答案:D

  • 第3题:

    When installing a new PCIe network card, when should manufacturer software and drivers beinstalled?()

    • A、Before inserting the PCIe network card in the case
    • B、After inserting the new PCIe network card in the case
    • C、They will be automatically loaded after installation
    • D、Load them concurrently with the PCIe network card

    正确答案:A

  • 第4题:

    A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()

    • A、 Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.
    • B、 Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.
    • C、 Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.
    • D、 Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

    正确答案:D

  • 第5题:

    A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()

    • A、 vmstat and iostat data from the older machines 
    • B、 The number of CPUs that were installed in the original machines 
    • C、 Data from Workload Estimator (WLE) and IBM Performance Management (PM) 
    • D、 Performance data that is collected from the new system after it has been put into production

    正确答案:C

  • 第6题:

    A customer requires two 12X loops on their new POWER7 system. What is the smallest system that will support two loops?()

    • A、Power 710
    • B、Power 720
    • C、Power 730
    • D、Power 740

    正确答案:D

  • 第7题:

    A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached; One 4-port 1Gbps IVE adapterPowerVM Standard Edition; They need to add a GX++ adapter and cable it to an I/O drawer. Which of the following must also be ordered?()

    • A、A second IVE adapter
    • B、A second processor card
    • C、PowerVM Enterprise Edition
    • D、An additional cable-management arm

    正确答案:B

  • 第8题:

    A customer currently has five partitioned POWER4 systems and is adding new systems.  When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()

    • A、Order a new HMC to support the p5 system.
    • B、Attach the new p5 system to the existing HMC.
    • C、Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.
    • D、Do nothing.  This system does not require an HMC.

    正确答案:A

  • 第9题:

    单选题
    In the event of a catastrophic disaster, after which you need to replace the entire UCS blade system (that is, new fabric interconnects, new IOMs, new chassis, and new blades), what type of backup would provide the most complete set of information?()
    A

     logical configuration

    B

     all configuration

    C

     full state

    D

     system configuration


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A technician has just installed an upgraded graphics card. The computers power turns off before itfinishes booting. Which of the following is the cause of the problem? ()
    A

    The monitor cannot display the increased resolution that is a feature of the new graphics card.

    B

    The power supply does not provide enough wattage to power the new graphics card.

    C

    The new graphics card is incompatible with the existing processor.

    D

    The computer does not have enough RAM to support the new graphics card.


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()
    A

     vmstat and iostat data from the older machines 

    B

     The number of CPUs that were installed in the original machines 

    C

     Data from Workload Estimator (WLE) and IBM Performance Management (PM) 

    D

     Performance data that is collected from the new system after it has been put into production


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    A customer requires two 12X loops on their new POWER7 system. What is the smallest system that will support two loops?()
    A

    Power 710

    B

    Power 720

    C

    Power 730

    D

    Power 740


    正确答案: B
    解析: 暂无解析

  • 第13题:

    An HP customer would like to discuss IBM system advantages. Their current system platform is a partitioned HP rp8400. Which of the following pSeries systems and advantages should be discussed?()

    • A、p630. Maximum partitions, maximum storage, I/O bus speed
    • B、p670. Maximum partitions, maximum memory, number of I/O slots
    • C、p655. Maximum number of CPUs, processor speed, number of I/O slots
    • D、p690. Maximum number of CPUs, peak system bandwidth, peak I/O bandwidth

    正确答案:B

  • 第14题:

    Which of the following is MOST critical when installing a new processor in an existing system?()

    • A、Thermal paste
    • B、Fans
    • C、Drive speeds
    • D、Cable management

    正确答案:A

  • 第15题:

    A technician has just installed an upgraded graphics card. The computers power turns off before itfinishes booting. Which of the following is the cause of the problem? ()

    • A、The monitor cannot display the increased resolution that is a feature of the new graphics card.
    • B、The power supply does not provide enough wattage to power the new graphics card.
    • C、The new graphics card is incompatible with the existing processor.
    • D、The computer does not have enough RAM to support the new graphics card.

    正确答案:B

  • 第16题:

    A customer has a POWER6 520 system with 6 partitions. They plan to upgrade their system and need to determine the current hardware configuration of the partitions before making any upgrade decisions. What is needed to read the exported system plan and design the new system?()

    • A、e-Config
    • B、System Planning Tool (SPT)
    • C、IBM Workload Estimator (WLE)
    • D、IBM Performance Monitor (PM)

    正确答案:B

  • 第17题:

    A customer is evaluating using the PCIe SSD adapter for the system boot in their new Power 750. Redundancy and hot-swap capability are required. What configuration supports the customer requirements?()

    • A、Configure the PCIe SSD adapter and drive modules as a JBOD
    • B、Configure a pair of mirrored PCIe SSD adapters and drive modules
    • C、Configure the PCIe SSD adapter and drive modules in a RAID-6 array
    • D、Configure the PCIe SSD adapter and drive modules in a RAID-5 array

    正确答案:B

  • 第18题:

    A customer requires an infrastructure to support disaster recovery of critical applications between two remote data centers. One data center is in Tokyo and one is in Beijing. The customer’s Recovery Point Objective (RPO) requires a six-hour window for a bandwidth of 100 MB/s and a new storage system for a total of 4 TB of data. They estimate 100 MB of new data produced hourly. What data synchronization method would be recommended to meet the requirements()

    • A、Metro Mirror
    • B、FlashCopy
    • C、Global Mirror
    • D、Snapshot

    正确答案:C

  • 第19题:

    A system administrator is deploying a new POWER5 server. The application requires AIX 5L V5.2.  Which of the following virtualization technologies can be used?()

    • A、DLPAR
    • B、Micro-Partitioning
    • C、Virtual Storage
    • D、Virtual Ethernet

    正确答案:A

  • 第20题:

    Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()

    • A、Add the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adapters
    • B、Power down the partitions,run the diag a command when the system is brought back up and reconfigure the network cards
    • C、Use the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after reboot
    • D、Detach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure

    正确答案:D

  • 第21题:

    单选题
    A customer has a POWER6 520 system with 6 partitions. They plan to upgrade their system and need to determine the current hardware configuration of the partitions before making any upgrade decisions. What is needed to read the exported system plan and design the new system?()
    A

    e-Config

    B

    System Planning Tool (SPT)

    C

    IBM Workload Estimator (WLE)

    D

    IBM Performance Monitor (PM)


    正确答案: D
    解析: 暂无解析

  • 第22题:

    单选题
    What is a design consideration when using existing PCIe I/O drawers in a maximum bandwidth/throughput configuration on a new Power 750 system?()
    A

    The new system requires 1 installed processor card for the GX++ bus adapter

    B

    The new system requires a minimum of 2 installed processor cards for the GX++ bus adapter

    C

    The new system requires a minimum of 3 installed processor cards and the HPC InfiniBand cluster adapter

    D

    The new system requires 1 installed processor card for the GX++ bus adapter and the HPC InfiniBand  cluster adapter


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    When installing a new PCIe network card, when should manufacturer software and drivers beinstalled?()
    A

    Before inserting the PCIe network card in the case

    B

    After inserting the new PCIe network card in the case

    C

    They will be automatically loaded after installation

    D

    Load them concurrently with the PCIe network card


    正确答案: C
    解析: 暂无解析