A customer is planning to implement a new x445 in their datacenter.Which TWO of the following should the customer prepare prior to the implementation to ensure a trouble free installation?()A、Install the exhaust fan on top of the IBM NetBAY 42 Enterprise 

题目

A customer is planning to implement a new x445 in their datacenter.Which TWO of the following should the customer prepare prior to the implementation to ensure a trouble free installation?()

  • A、Install the exhaust fan on top of the IBM NetBAY 42 Enterprise rack for extra cooling
  • B、Ensure a 260V power source for the x445 and BladeCenter is available for fully redundant power
  • C、Ensure a 220v power source for the x445 is available for fully redundant power
  • D、Install the new 10GBit Ethernet network to take advantage of the new network switch in the x445.
  • E、Have their Network Operation Staff review and assist connecting the new server to their existing network.

相似考题
参考答案和解析
正确答案:C,E