() is one of the quality planning outputs.
第1题:
● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.
(71)
A.risk
B.problem
C.result
D.data
第2题:
According to the principles or the six key points proposed by Harvard Business School to judge the quality of an elevator pitch, it may be inferred that the example given in lesson five could be a defective one.()
第3题:
Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.
A.risk
B.problem
C.result
D.data
第4题:
is one of the quality planning outputs. A.Scope base line B.Cost ofquality C.Product specification D.Quality checklist
第5题:
The project team members should also be aware of one of the fundamental tenets of modem quality management: quality is planned, designed and built in, not(72).
A.executed in
B.inspected in
C.check-in
D.look-in
第6题:
Software quality assurance is now an(71)sub-discipline of software engineering. As Bucldy and Oston point out,(72)software quality assurance is likely to lead to an ultimate(73)of software costs. However, the major hurdle in the path of software management in this area is the lack of(74)software standards. The development of accepted and generally applicable standards should be one of the principal goals of(75)in software engineering.
A.emerging
B.emergent
C.engaging
D.evolve
第7题:
第8题:
The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()
第9题:
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
第10题:
as a result of the effect of one on the other
always at the same time
independently of each other
when the demand exceeds the supply
第11题:
Benchmarking
Quality metric
Quality checklist
Brainstornung
第12题:
executedin
inspectedin
check-in
look-in
第13题:
● (75)is one of the quality planning outputs.
(75)
A. Scope base line
B. Cost of quality
C. Product specification
D. Quality checklist
第14题:
●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.
(71)A. Benchmarking
B. Quality metric
C. Quality checklist
D. Brainstorming
第15题:
is one of the quality planning outputs.
A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist
第16题:
● Project()is an uncertain event or condition that ,if it occurs ,has a positive or a negative effect on at least one project objective ,such as time ,cost ,scope or quality()A. risk B. problem C. result D. data
第17题:
A.than
B.above
C.over
D.to
第18题:
第19题:
第20题:
Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.
第21题:
think of something extraordinary
experience delight at an old age
feel the magic quality of pleasure
enjoy what one has at the moment
第22题:
Scope base line
Cost of quality
Product specification
Quality checklist
第23题:
Benchmarking
Quality metric
Quality checklist
Brainstorming