() is one of the quality planning outputs.A、Scope base lineB、Cost of qualityC、Product specificationD、Quality checklist

题目

() is one of the quality planning outputs.

  • A、Scope base line
  • B、Cost of quality
  • C、Product specification
  • D、Quality checklist

相似考题
更多“() is one of the quality planni”相关问题
  • 第1题:

    ● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.

    (71)

    A.risk

    B.problem

    C.result

    D.data


    正确答案:A

  • 第2题:

    According to the principles or the six key points proposed by Harvard Business School to judge the quality of an elevator pitch, it may be inferred that the example given in lesson five could be a defective one.()


    参考答案:对

  • 第3题:

    Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

    A.risk

    B.problem

    C.result

    D.data


    正确答案:A
    解析:风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

  • 第4题:

    is one of the quality planning outputs. A.Scope base line B.Cost ofquality C.Product specification D.Quality checklist


    正确答案:D
    质量检查表(QualityChecklist)是制定项目质量管理计划过程的成果之一。
    表6-6给出了本份上午试卷问题1~问题75的参考答案,供读者练习时参考,以便查缺补漏。读者可按每空1分的评分标准得出测试分数,从而大致评估自己对这些知识点的掌握程度。

  • 第5题:

    The project team members should also be aware of one of the fundamental tenets of modem quality management: quality is planned, designed and built in, not(72).

    A.executed in

    B.inspected in

    C.check-in

    D.look-in


    正确答案:B
    解析:项目团队成员应该注意到现代质量管理的一条基本准则是:质量是计划、设计出来的,不是检查出来的。

  • 第6题:

    Software quality assurance is now an(71)sub-discipline of software engineering. As Bucldy and Oston point out,(72)software quality assurance is likely to lead to an ultimate(73)of software costs. However, the major hurdle in the path of software management in this area is the lack of(74)software standards. The development of accepted and generally applicable standards should be one of the principal goals of(75)in software engineering.

    A.emerging

    B.emergent

    C.engaging

    D.evolve


    正确答案:A
    解析:现在软件质量保证足软件工程的新兴的附属要求。正如Buckly和Oston所指出,有效的软件质量保证很可能影响软件成本最终的增长。不过,在软件管理过程中主要的障碍是缺乏可用的软件标准。适用性软件标准的开发应该是在软什工程里主要研究目标之一。

  • 第7题:

    ()is one of the quality planning outputs.

    A.Scope base line
    B.Cost of quality
    C.Product specification
    D.Quality checklist

    答案:D
    解析:
    是制定项目质量管理计划过程的成果之一。
    A.范围基线 B.质量成本
    C.产品规范 D.质量检查表

  • 第8题:

    The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()

    • A、executedin
    • B、inspectedin
    • C、check-in
    • D、look-in

    正确答案:B

  • 第9题:

    Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    • A、Benchmarking
    • B、Quality metric
    • C、Quality checklist
    • D、Brainstornung

    正确答案:A

  • 第10题:

    单选题
    According to the passage,we can see that lower prices and better quality occur______.
    A

    as a result of the effect of one on the other

    B

    always at the same time

    C

    independently of each other

    D

    when the demand exceeds the supply


    正确答案: B
    解析:

  • 第11题:

    单选题
    Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
    A

    Benchmarking

    B

    Quality metric

    C

    Quality checklist

    D

    Brainstornung


    正确答案: C
    解析: 暂无解析

  • 第12题:

    单选题
    The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()
    A

    executedin

    B

    inspectedin

    C

    check-in

    D

    look-in


    正确答案: C
    解析: 该题的关键词为"planned、designed、built in",其关键的语句结构为"quality(主语)is planned,designed and built in,not()(谓语)",含义为"质量是通过计划、设计、制造而得到的,不是什么",易知此处应该选择与计划、设计、制造方式相反的观点,结合四个选项,CD首先可以排除,因为从形式上应该选择过去分词形式。选项A的含义与built in相似,排除法可以得到选项B,其实这句话是质量管理中一个非常著名的说法,原文可译为:项目组成员应该知道现代质量管理的一个基本原则,即质量是通过计划、设计和制造得到的,而不是通过事后检查得到。

  • 第13题:

    ● (75)is one of the quality planning outputs.

    (75)

    A. Scope base line

    B. Cost of quality

    C. Product specification

    D. Quality checklist


    正确答案:D

  • 第14题:

    ●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    (71)A. Benchmarking

    B. Quality metric

    C. Quality checklist

    D. Brainstorming


    正确答案:A

  • 第15题:

    is one of the quality planning outputs.

    A.Scope base line

    B.Cost of quality

    C.Product specification

    D.Quality checklist


    正确答案:D

  • 第16题:

    ● Project()is an uncertain event or condition that ,if it occurs ,has a positive or a negative effect on at least one project objective ,such as time ,cost ,scope or quality()A. risk B. problem C. result D. data


    正确答案:A
    项目风险是一种不确定的事件或条年,一旦发生,至少会对一个项目目标,比如时间、成本、范围或质量造成正面或负面的影响。

  • 第17题:

    Do you think that the quality of the product is superior ___ that one’s?

    A.than

    B.above

    C.over

    D.to


    答案:D

  • 第18题:

    Generally speaking, quality inspection is ( ) of visual inspection and interior inspection.
    A. composed B. each
    C. one D. result


    答案:A
    解析:

  • 第19题:

    According to the maxim of ( ) suggested by Grice, one should speak truthfully.

    A.quality
    B.manner
    C.relation
    D.quantity

    答案:A
    解析:
    考查会话原则。质量准则规定所说的话力要求真实,不要说自知为虚假的话,不要说缺乏足够证据的话。

  • 第20题:

    Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.

    • A、Benchmarking
    • B、Quality metric
    • C、Quality checklist
    • D、Brainstorming

    正确答案:A

  • 第21题:

    单选题
    According to the author, happiness lies in the ability to ______.
    A

    think of something extraordinary

    B

    experience delight at an old age

    C

    feel the magic quality of pleasure

    D

    enjoy what one has at the moment


    正确答案: C
    解析:
    先看一下四个选项的意思:A“非常规的去想事情”,B“年纪大一些时经历快乐的事”,C “感受快乐的魔幻”,D“享受我们当下拥有的东西”。而文章最后一句“It’s not wishing for what we don’t have,but enjoying what we do possess. ”点出“快乐是要享受我们所拥有的”,所以是D。

  • 第22题:

    单选题
    () is one of the quality planning outputs.
    A

    Scope base line

    B

    Cost of quality

    C

    Product specification

    D

    Quality checklist


    正确答案: A
    解析: 中文解释:______是制定项目质量管理计划过程的成果之一。 A.范围基线 B.质量成本 C.产品规范 D.质量检查表

  • 第23题:

    单选题
    Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.
    A

    Benchmarking

    B

    Quality metric

    C

    Quality checklist

    D

    Brainstorming


    正确答案: C
    解析: 参考答案:A