Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement

题目

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

  • A、Integration
  • B、Scope
  • C、Configuration
  • D、Requirement

相似考题
参考答案和解析
正确答案:D
更多“Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement”相关问题
  • 第1题:

    ● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

    t

    A.Integration

    B.Scope

    C.Configuration

    D.Requiremen


    正确答案:B

  • 第2题:

    Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning D.Communication


    正确答案:D
    项目沟通管理是使用所需过程以确保及时、恰当地产生、收集、分发、存储、收回和最终处置项目信息的知识域。

  • 第3题:

    The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A、project scope statement

    B、work package

    C、WBS

    D、project scope plan


    参考答案:C

  • 第4题:

    In the project management context,(68)includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

    A.integration

    B.scope

    C.process

    D.charter


    正确答案:A
    解析:在项目管理语境中,“整体”包含了统一、合并、联接的特性,以及对于完成项目、成功满足顾客和其他干系人的需求及管理期望至关重要的整体行动。

  • 第5题:

    Project(74)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

    A.Integration

    B.Time

    C.Planning

    D.Communication


    正确答案:D
    解析:项目沟通管理是使用所需过程以确保及时、恰当地产生、收集、分发、存储、收回和最终处置项目信息的知识域。

  • 第6题:

    A project management technique that is currently in widespread use is the ( ) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.

    A.Functional decomposition diagram
    B.Work Breakdown Structure
    C.Structure Chart
    D.Organizational Structure

    答案:B
    解析:

  • 第7题:

    Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.

    A.Developing project charter
    B.Developing project management plan
    C.Analyzing project risks
    D.Monitoring and controlling project

    答案:C
    解析:
    项目整合管理包括在项目管理过程组中识别、定义、组合、统一和协调各种过程和项目管理活动的过程和活动。识别项目风险过程不属于项目整合管理。
    A制定项目章程,B制定项目管理计划,C识别项目风险,D指导与管理项目。

  • 第8题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A. Create scopE
    B. Project stakeholder management
    C. Project scope management
    D. Project cost management

    答案:C
    解析:

  • 第9题:

    The () describes, in detail, the project's deliverables and the work required to create those deliverables.

    • A、project scope statement
    • B、project requirement
    • C、project charter
    • D、product specification

    正确答案:A

  • 第10题:

    Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.

    • A、Integration
    • B、Time
    • C、Planning
    • D、Communication

    正确答案:D

  • 第11题:

    单选题
    Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
    A

    Integration

    B

    Scope

    C

    Configuration

    D

    Requirement


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
    A

    Integration

    B

    Time

    C

    Planning

    D

    Communication


    正确答案: A
    解析: 暂无解析

  • 第13题:

    Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

    A.Develop Schedule

    B.Estimate Activity Resources

    C.Define Activities

    D.Sequence Activities


    正确答案:A
    解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。

  • 第14题:

    A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.

    A.Structure Chart

    B.Organizational Structure

    C.Work Breakdown Structure

    D.Functional decomposition diagram


    正确答案:C

  • 第15题:

    Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.

    A.Integration

    B.Configuration

    C.Scope

    D.Requirement


    正确答案:C

  • 第16题:

    Project(69)Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    A.Integration

    B.Scope

    C.Configuration

    D.Requirement


    正确答案:B
    解析:项目范围里管理包括为确保项目包含且仅只包含成功完成项目必需工作的所需过程。

  • 第17题:

    The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    A.project scope statement
    B.project requirement
    C.project charter
    D.product specification

    答案:A
    解析:
    项目范围说明书详细描述了项目的可交付物以及为创建这些可交付物所需的工作。
    A.项目范围说明书B.项目需求C.项目章程 D.产品规范

  • 第18题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A:Create scopE
    B:Project stakeholder management
    C:Project scope management
    D:Project cost management

    答案:C
    解析:

  • 第19题:

    The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A.Project scope statement
    B.Work package
    C.WBS
    D.Project scope plan

    答案:C
    解析:
    ()是项目团队为完成项目目标和创建所需可交付成果而执行的整个工作范围的分层分解。
    A.项目范围说明书B.工作包C.WBS?D.项目范围计划

  • 第20题:

    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    • A、Product scope description
    • B、Project objectives
    • C、Stakeholder Analysis
    • D、The project scope statement

    正确答案:D

  • 第21题:

    Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

    • A、Integration
    • B、Time
    • C、Planning
    • D、Communication

    正确答案:B

  • 第22题:

    Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:B

  • 第23题:

    单选题
    Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.
    A

    Integration

    B

    Scope

    C

    Configuration

    D

    Requirement


    正确答案: B
    解析: 该题的关键词为"all the work required, only the work required",其语句结构为"Project()Management(主语)includes(谓语)the processes",含义为"项目什么管理包含过程",仅根据关键词便可判断出应该与项目范围管理紧密相关,在结合语句分析,应该选择项目范围管理,即Scope。