The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.A、PlanningB、ExecutingC、Monitoring and ControllingD、Closing

题目

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

  • A、Planning
  • B、Executing
  • C、Monitoring and Controlling
  • D、Closing

相似考题
更多“The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.A、PlanningB、ExecutingC、Monitoring and ControllingD、Closing”相关问题
  • 第1题:

    ● The inputs of developing project management plan do not include (72).

    (72)

    A. project charter

    B. stakeholder management strategy

    C. project scope statement

    D. outputs from planning processes


    正确答案:B

  • 第2题:

    The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter


    正确答案:B
    制定项目管理计划过程定义、准备、集成和协调所有的分计划,以形成项目管理计划 。

  • 第3题:

    The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out


    正确答案:B
    执行(Executing)过程组由为达成项目要求而在项目管理计划中定义的工作的过程组成。

  • 第4题:

    The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A、project scope statement

    B、work package

    C、WBS

    D、project scope plan


    参考答案:C

  • 第5题:

    The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75).

    A.Project Scope Statement

    B.Project Management Plan

    C.Forecasts

    D.Project Charter


    正确答案:B

  • 第6题:

    Project(69)Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    A.Integration

    B.Scope

    C.Configuration

    D.Requirement


    正确答案:B
    解析:项目范围里管理包括为确保项目包含且仅只包含成功完成项目必需工作的所需过程。

  • 第7题:

    The inputs of developing project management plan do not include().

    A. project charter
    B. stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括(72)
    A.项目章程 B. 干系人管理策略
    C.项目范围说明书 D. 计划过程输出

  • 第8题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A:Create scopE
    B:Project stakeholder management
    C:Project scope management
    D:Project cost management

    答案:C
    解析:

  • 第9题:

    A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).

    A.task
    B.work
    C.sequence
    D.activity

    答案:C
    解析:
    表示序列的意思。
    附(参考翻译):一个项目是一个独特的、复杂的、相互关联的活动的[临时]序列,有一个目标或目的,必须在特定的时间、预算内和根据规范完成。项目管理是一个范围界定、计划、人员配置、组织、指导和控制可接受系统开发的过程,在规定的时间内以最低的成本进行。对于任何系统开发项目,有效的项目管理都是必要的,以确保项目在截止日期前完成,在可接受的预算内开发,并满足客户的期望和规范,项目管理是从项目开始时开始的过程,延伸到一个项目中,直到项目完成才达到顶点。良好的项目管理的先决条件是定义良好的系统开发过程。过程管理是一项持续的活动,它记录、管理和改进组织为系统开发所选择的方法(“过程”),过程管理涉及应用于所有项目的活动、可交付成果和质量标准。

  • 第10题:

    The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A.Project scope statement
    B.Work package
    C.WBS
    D.Project scope plan

    答案:C
    解析:
    ()是项目团队为完成项目目标和创建所需可交付成果而执行的整个工作范围的分层分解。
    A.项目范围说明书B.工作包C.WBS?D.项目范围计划

  • 第11题:

    Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:B

  • 第12题:

    单选题
    The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
    A

    Planning

    B

    Executing

    C

    Monitoring and Controlling

    D

    Closing


    正确答案: D
    解析: 该题的关键词为"accomplish the project's requirements",其语句结构为"The()Process Group(主语)consists of(谓语)the processes used to complete the work defined",含义为"用于完成工作的过程组成什么过程组",所以可知重点描述为"完成工作",根据项目管理五个过程组的特点,选择Executing(执行)过程组,其他选项容易排除。

  • 第13题:

    The(69)Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

    A.Plannlng

    B.Executing

    C.Monitoring and Controlling

    D.Closing


    正确答案:B
    解析:执行过程组由用于完成为达成项目要求而在项目管理计划中定义的工作的过程组成。

  • 第14题:

    The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes


    正确答案:B
    制定项目管理计划的输入不包括干系人管理策略(stakeholder management strategy)。

  • 第15题:

    The(14)Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

    A.Planning

    B.Executing

    C.Monitoring and Controlling

    D.Closing


    正确答案:B
    解析:执行过程组由用于完成为达成项目要求而在项目管理计划中定义的工作的过程组成。

  • 第16题:

    Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.

    A.Integration

    B.Configuration

    C.Scope

    D.Requirement


    正确答案:C

  • 第17题:

    ()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.

    A.Identity risks

    B.Control risks

    C.Plan risk responses

    D.Plan risk management


    正确答案:B

  • 第18题:

    The Develop Project Management Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ( )

    A. Project Scope Statement
    B.Project Management Plan
    C.Forecasts
    D.Project Charter

    答案:B
    解析:
    项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到(75)。

    A. 项目范围说明书 B. 项目管理计划

    C. 项目预测 D. 项目章程

  • 第19题:

    The inputs of developing project management plan do not include()

    A.project charter
    B.stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括:A.项目章程 B.利益相关者管理策略 C.项目范围描述 D.计划过程输出

  • 第20题:

    Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.

    A.Developing project charter
    B.Developing project management plan
    C.Analyzing project risks
    D.Monitoring and controlling project

    答案:C
    解析:
    项目整合管理包括在项目管理过程组中识别、定义、组合、统一和协调各种过程和项目管理活动的过程和活动。识别项目风险过程不属于项目整合管理。
    A制定项目章程,B制定项目管理计划,C识别项目风险,D指导与管理项目。

  • 第21题:

    The inputs of developing project management plan do not include ().

    A.project charter
    B.stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括 () 。
    A.项目章程 B.干系人管理策略
    C.项目范围说明书 D.计划过程输出

  • 第22题:

    The inputs of developing project management plan do not include()

    • A、project charter
    • B、stakeholder management strategy
    • C、project scope statement
    • D、outputs from planning processes

    正确答案:B

  • 第23题:

    Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:D