更多“A milestone is a significant ( )”相关问题
  • 第1题:

    A calendar that identifies when a project may be performed on an activity is called a:

    A.Project calendar.

    B.Resource calendar.

    C.Milestone point.

    D.Key point.

    E.Work unit.


    正确答案:A
    A

  • 第2题:

    The most common types of schedules are Gantt charts, milestone charts, line of balance, and:

    A.Networks.

    B.Time phased events.

    C.Calendar integrated activities.

    D.A and C only.

    E.B and C only.


    正确答案:A
    A

  • 第3题:

    178 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:

    A. Work breakdown structure

    B. milestone review and schedule technique

    C. cost/schedule control system

    D. planning programming budget system

    E. program and evaluation review technique


    正确答案:A

  • 第4题:

    ● The purpose of a dummy activity in an activity-on-arrow diagram is to:

    A Identify a task that could be replaced by another.

    B Take the slack time into account.

    C Show a task that is not necessarily needed.

    D Denote a milestone.

    E Show a dependency relationship.


    正确答案:E

  • 第5题:

    John and his brother differ in personality even if their differences in age are not significant. 英译汉


    参考答案:尽管约翰和他哥哥在年纪上相差不大,但他们的个性却不相同。

  • 第6题:

    ( )is ameasurable,verifiable work poduct such as specification,feasibility study report,detail document,or working prototype。 A.Deliverable B.Project charter C.Earned value D.Milestone


    正确答案:A
    可交付物(Deliverable)是指像规格说明书、可行性研究报告、详细设计文档或可运转的原型之类的可测量、可验证的工作产品。

  • 第7题:

    Configuration management is the process of managing change in hardware,software,firmware,documentation,measurements,etc.As change requires an initial state and next state,the marking of significant states within a series of several changes becomes important.The identification of significant states within the revision history of a configuration item is the central purpose of(75) identification.

    A.baseline

    B.value

    C.cost

    D.control


    正确答案:A
    解析:配置管理是在硬件、软件、固件、文件、测量等的过程管理的变化,作为变化需要有一个初始状态和下一个状态,标识上一状态变化非常重要,配置项目需确定重要状态的修订历史记录,主要目的是基线的确定。

  • 第8题:

    ( ) is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.

    A.gantt chart
    B.project histogram
    C.milestone chart
    D.project flowchart

    答案:A
    解析:
    甘特图是一类描述项目进度的图表。它说明了一个项目的开始和结束时间。A.甘特图 B.项目直方图C.里程碑图 D.项目流程图

  • 第9题:

    Very significant


    正确答案: 极显著。若试验结果由误差造成的概率Р=<0.01,则称样本统计数的差异为极显著。

  • 第10题:

    The() defines the phases that connect the beginning of a project to its end.

    • A、schedule
    • B、project life cycle
    • C、temporary
    • D、milestone

    正确答案:D

  • 第11题:

    单选题
    Which statement describes the process ID that is used to run OSPF on a router ?()
    A

    It is locally significant and must be the same throughout an area

    B

    It is globally significant and is used to represent the AS number

    C

    It is locally significant and is used to identify an instance of the OSPF database

    D

    It is globally significant and is used to identify OSPF stub areas


    正确答案: C
    解析: 暂无解析

  • 第12题:

    单选题
    What could cause a significant difference between actual chain tension and the tension measured by the tensiometer? ()
    A

    The type of anchor and mooring line being used

    B

    The type of bottom in which the ship is anchored

    C

    A significant difference between air and water temperature

    D

    The chain contacting a chock or fairlead between the tensiometer and the lower swivel fairlead


    正确答案: C
    解析: 暂无解析

  • 第13题:

    A project element which lies between two events is called:

    A.An activity.

    B.A critical path method.

    C.A slack milestone.

    D.A timing slot.

    E.A calendar completion point.


    正确答案:A
    A

  • 第14题:

    93 The most common types of schedules are Gantt charts, milestone charts, line of balance, and: A. Networks.

    B. Time phased events.

    C. Calendar integrated activities.

    D. A and C only.

    E. B and C only.


    正确答案:A

  • 第15题:

    ● All of the following are categories of a milestone in a schedule except:

    A End date.

    B Contract dates.

    C Key events scheduled.

    D Imposed dates.

    E Task duration.


    正确答案:E

  • 第16题:

    Small talk is conversation that()leads to insight into anything significant.

    A、seldom

    B、often


    参考答案:A

  • 第17题:

    The(67)defines the phases that connect the beginning of a project to its end.

    A.schedule

    B.project life cycle

    C.temporary

    D.milestone


    正确答案:B
    解析:项目生命周期定义了从项目开始直至结束的项目阶段。

  • 第18题:

    northern ireland is significant because of its manufacturing industry. ()


    参考答案:错误

  • 第19题:

    is ameasurable,verifiable work poduct such as specification.Feasibility study report,detail document,or working prototype.

    A.Deliverable

    B.Project charter

    C.Earned value

    D.Milestone


    正确答案:A

  • 第20题:

    () is a measurable, verifiable work product such as a specification, feasibilitystudy report, detail design document, or working prototype.

    A.Milestone
    B.Deliverable
    C.ETC
    D.BAC

    答案:B
    解析:
    可交付物是指像规格说明书、可行性研究报告、详细设计文档或可运转的原型之类的可测量、可验证的工作产品。

  • 第21题:

    Which statement describes the process ID that is used to run OSPF on a router ?()

    • A、It is locally significant and must be the same throughout an area
    • B、It is globally significant and is used to represent the AS number
    • C、It is locally significant and is used to identify an instance of the OSPF database
    • D、It is globally significant and is used to identify OSPF stub areas

    正确答案:C

  • 第22题:

    单选题
    The most significant feature of Irish landscape is()which provide peat used for fuel.
    A

    bogs

    B

    streams

    C

    islands

    D

    cliffs


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    A milestone is a significant ( ) in a project.
    A

    activity

    B

    event

    C

    phase

    D

    process


    正确答案: D
    解析: 暂无解析

  • 第24题:

    单选题
    The underlined word “significant” (in Paragraph 1) most probably means “_____”.
    A

    strange

    B

    terrible

    C

    important

    D

    difficult


    正确答案: A
    解析:
    根据下文,发生在1990年的世界事件:东西德统一,World Wide Web 的诞生。我们不难推测,significant是指“重要,重大”。故选C项。