The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()A、executedinB、inspectedinC、check-inD、look-in

题目

The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()

  • A、executedin
  • B、inspectedin
  • C、check-in
  • D、look-in

相似考题
参考答案和解析
正确答案:B
更多“The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()A、executedinB、inspectedinC、check-inD、look-in”相关问题
  • 第1题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    A.Project

    B.project management team

    C.performingorganization

    D.customer


    参考答案:C

    该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

  • 第2题:

    Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object


    正确答案:C

    项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

  • 第3题:

    ●The quality management plan should describe how the project management team will implement its quality (73).

    (73) A. improvement

    B. control

    C. policy

    D. information


    正确答案:C

  • 第4题:

    The quality management plan should describe how the project management team will implement its quality(73).

    A. improvement

    B. control

    C. policy

    D. information


    正确答案:C
    质量管理计划应说明项目管理团队如何来实施执行其质量。(73)A.改进B.控制C.政策D.信息。

  • 第5题:

    Project Quality Management must address the management of the project and the(72)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

    A.performance

    B.process

    C.product

    D.object


    正确答案:C
    解析:项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

  • 第6题:

    ()is the application of planned,systematic quality activities to ensure thatthe project will employ all processes needed to meet requirements.

    A.Quality assurance(QA)
    B.Quality planning
    C.Quality control(QC)
    D.Quality costs

    答案:A
    解析:
    质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。质量成本是指为满足质量要求所付出的主要成本。质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项 A 是质量保证(QA),选项B 是质量计划,选项 C 是质量控制(QC),选项 D 是质量成本。因此应选择 A。

  • 第7题:

    ()is the application of planned,systematic.quality activities to ensure that the project will employ all processes to meet requirements.

    A.Quality assurance
    B.Quality planning
    C.Quality control
    D.Quality cost

    答案:A
    解析:
    翻译:
    ()是计划的应用于系统的质量活动,确保该项目将采用所有流程来满足需求。
    A.质量保证B..质量计划C.质量控制D..质量成本

  • 第8题:

    Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

    • A、performance
    • B、process
    • C、product
    • D、object

    正确答案:B

  • 第9题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    • A、Project
    • B、project management team
    • C、performingorganization
    • D、customer

    正确答案:C

  • 第10题:

    The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()

    • A、Evaluate phase exit milestones using sufficiency criteria
    • B、Flexible entry and exit criteria to minimize schedule delays
    • C、Quality measures reported only to the project steering committee
    • D、Many work teams with few members to maximize the number of deliverable hand-offs

    正确答案:A

  • 第11题:

    单选题
    Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
    A

    Benchmarking

    B

    Quality metric

    C

    Quality checklist

    D

    Brainstornung


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()
    A

    executedin

    B

    inspectedin

    C

    check-in

    D

    look-in


    正确答案: C
    解析: 该题的关键词为"planned、designed、built in",其关键的语句结构为"quality(主语)is planned,designed and built in,not()(谓语)",含义为"质量是通过计划、设计、制造而得到的,不是什么",易知此处应该选择与计划、设计、制造方式相反的观点,结合四个选项,CD首先可以排除,因为从形式上应该选择过去分词形式。选项A的含义与built in相似,排除法可以得到选项B,其实这句话是质量管理中一个非常著名的说法,原文可译为:项目组成员应该知道现代质量管理的一个基本原则,即质量是通过计划、设计和制造得到的,而不是通过事后检查得到。

  • 第13题:

    ● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

    A.performance

    B.process

    C.product

    D.object


    正确答案:C

  • 第14题:

    ● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs


    正确答案:A
    质量保证是一项有计划的、系统的质量活动,以确保项目的所有过程达到并符合要求。

  • 第15题:

    The project team members should also be aware of one of the fundamental tenets of modem quality management: quality is planned, designed and built in, not(72).

    A.executed in

    B.inspected in

    C.check-in

    D.look-in


    正确答案:B
    解析:项目团队成员应该注意到现代质量管理的一条基本准则是:质量是计划、设计出来的,不是检查出来的。

  • 第16题:

    The quality management plan should describe how the project management team will implement its quality(73).

    A.improvement

    B.control

    C.policy

    D.information


    正确答案:C
    质量管理计划应说明项目管理团队如何来实施执行其质量(73)。A.改进B.控制C.政策D.信息。

  • 第17题:

    ( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

    A.Quality assurance(QA)
    B.Quality planning
    C.Quality control(QC)
    D.Quality costs

    答案:A
    解析:
    质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。
    质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。
    质量成本是指为满足质量要求所付出的主要成本。
    质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项A是质量保证(QA),选项B是质量计划,选项C是质量控制(QC),选项D是质量成本。因此应选择A。

  • 第18题:

    ( )The process of translating the quality management plan into eecutable quality activities that incorporate the organization's quality policies into the project.

    A:Munage quality
    B:Quality audit
    C:Quality metrics
    D:Quality improvement

    答案:C
    解析:

  • 第19题:

    Quality planning tools are often used to help plan effective quality management activities. ( ) is one of such tools,which involves comparing actual or planned project practices to other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    A.Benchmarking
    B.Quality metric
    C.Quality checklist
    D.Brainstorming

    答案:A
    解析:
    质量规划工具通常用来帮助计划有效的质量管理活动。(71)是一个这样的工具,它通过与别的项目比较实际的或计划的项目活动,产生改进的建议,并且提供一个基准用来衡量业绩的依据。A.基准 B.质量度量 C.质量检查表 D.头脑风暴

  • 第20题:

    Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.

    • A、Benchmarking
    • B、Quality metric
    • C、Quality checklist
    • D、Brainstorming

    正确答案:A

  • 第21题:

    Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    • A、Benchmarking
    • B、Quality metric
    • C、Quality checklist
    • D、Brainstornung

    正确答案:A

  • 第22题:

    单选题
    The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()
    A

    Evaluate phase exit milestones using sufficiency criteria

    B

    Flexible entry and exit criteria to minimize schedule delays

    C

    Quality measures reported only to the project steering committee

    D

    Many work teams with few members to maximize the number of deliverable hand-offs


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.
    A

    Benchmarking

    B

    Quality metric

    C

    Quality checklist

    D

    Brainstorming


    正确答案: C
    解析: 参考答案:A