During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.
第1题:
156 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is still the original baseline but annotated to reflect that a change has taken place.
C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E. Is the same since baseline schedules cannot change once the development phase is completed
第2题:
● The purpose of configuration management is to:
A insure drawings are updated
B control change throughout the project
C control change during the production only
D generate engineering change proposals
E inform. the project manager of changes
第3题:
● During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75)are necessary.
(75)
A. proceedings
B. controls
C. forecasting’s
D. prelibations
第4题:
The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria
A.work performance information
B.scope statement
C.change requests
D.process analysis
第5题:
The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
A.work performance information
B.scope statement
C.change requests
D.process analysis
第6题:
The project maintains a current and approved set of requirements over the life of the project by doing the following: .(73)all changes to the requirements . Maintaining the relationships among the requirements, the project plans, and the work products . ……
A.Monitoring
B.Managing
C.Gathering
D.Reducing
第7题:
第8题:
第9题:
第10题:
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()
第11题:
Which statement correctly describes the change tracking writer (CTWR) background process?()
第12题:
You need to recommend changes to the intranet site that meet the company’s technical requirements. What should you include in the recommendation?()
第13题:
33 The purpose of configuration management is to:
A. insure drawings are updated
B. control change throughout the project
C. control change during the production only
D. generate engineering change proposals
E. inform. the project manager of changes
第14题:
● The project maintains a current and approved set of requirements ovethe life of the project by doing the following:
· (73) all changes to the requirements
· Maintaining the relationships among the requirements, the project plansand the work products
· ……
(73)
A. Monitoring
B. Managing
C. Gathering
D. Reducin
第15题:
● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).
(73)
A.executive IT manager
B.project manger
C.change control board
D.project sponsor
第16题:
Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.
A.accuracy
B.approximation
C.specification
D.summary
第17题:
Requirements management is the process of ( 73 ),analyzing, tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome (product or service) should conform.
A.communicating
B.collecting
C.filing
D.documenting
第18题:
During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised(75)are necessary.
A.proceedings
B.controls
C.forecasting's
D.prelibations
第19题:
第20题:
第21题:
第22题:
( ) is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.
第23题:
During Company.com planning session, the LVM requirements for HACMP are provided. The administrator explains that there are five volume groups in the current production environment because filesystems constantly change due to the nature of the business. Maintenance outages are limited to one Saturday per month. There is some concern about the amount of time that will be required for outages once HACMP is installed. With HACMP,what will be the simplest methods of managing LVM changes while minimizing required downtime.()