Define Activities is the process ofidentifying the specific actions to be performed toproduce the()
第1题:
68 The Cost Performance Index (CPI) measures:
A. cost of work performed vs planned costs.
B. work performed vs cost of work performed.
C. work performed vs planned work.
D. direct costs vs indirect costs.
E. floating costs vs. sunk costs.
第2题:
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.
(74)
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第3题:
● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).
(71)
A. project elements
B. work drafts
C. work package
D. project deliverables
第4题:
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第5题:
The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria
A.work performance information
B.scope statement
C.change requests
D.process analysis
第6题:
The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
A.work performance information
B.scope statement
C.change requests
D.process analysis
第7题:
The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).
A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index
第8题:
第9题:
第10题:
The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.
第11题:
projectelements
work drafts
workpackage
projectdeliverables
第12题:
generating the SQL profile
testing and accepting the SQL profile
generating a list of candidate SQLs for tuning
adding tuned SQL plans into the SQL plan baseline
tuning each SQL statement in the order of importance
generating baselines that include candidate SQLs for tuning
第13题:
● Scope Management:
A entails managing the project's work content.
B is a subset of configuration management and as such is performed by CM specialists.
C is concerned with naming all activities performed, the end products which results and the resources consumed.
D is not a concern of the project manager.
E None of the above.
第14题:
Define Activities is the process of identifying the specific actions to be performed to produce the (71).
A.project elements
B.work drafts
C.work package
D.project deliverables
第15题:
● In order to achieve the major goals of business process improvement, process simplification and improvement, FAA managers need to fully understand the cost, time, and quality of activities performed by employees or machines throughout an entire organization. ABC methods enable () to cost out measurements to business simplification and process improvement. () A. computers B. managers C. clients D. consumers
第16题:
● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)
(75)
A. Project Scope Statement
B. Project Management Plan
C. Forecasts
D. Project Charter
第17题:
The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter
第18题:
The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75).
A.Project Scope Statement
B.Project Management Plan
C.Forecasts
D.Project Charter
第19题:
In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.
A.Activity list
B.Work Breakdown Structures
C.Activity Attributes
D.Milestone Lists
第20题:
第21题:
第22题:
Identify the activities performed as part of the Automatic SQL Tuning process in the maintenance window?()
第23题:
who have performed work for 14 hours
who have performed work in a scheduled rest period
who have performed work in a scheduled work period
who works hard