()means that every project has a definite beginning and a definite end.
第1题:
A negative cost variance and positive schedule variance means:
A The project is under budget and ahead of schedule
B The project is over budget and behind schedule
C The project is over budget and ahead of schedule
D The project will be overrun but ahead of schedule at completion
第2题:
40 For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?
A. project office memo
B. project office directive
C. project team meeting
D. formal report
E.counseling sessions
第3题:
171 Documented work authorization provide:
A. a means of effective internal coordination of the project's activities.
B. an audit trail of all work authorized from project initiation to completion
C.a means for communication of work activity between the project manager and the performing activities.
D. All of the above
E. A and B only
第4题:
78 Which of the following can the project manager use as a means of measuring project team effectiveness?
A. Absenteeism
B. Sponsor-approved salary increases
C. Efficiency of the team
D. Turnover of personnel
E. Grievances
第5题:
● The use of the project reports:
A are not necessary on small projects
B provides a means whereby various levels of authority can judge project performance
C provides insight into project areas and the effectiveness of the control systems
D All of the above
E B and C
第6题:
Every liquid has a pressure at which it will vaporize and this pressure varies with temperatureThe word “which” means _____.
A.a liquid
B.a pressure
C.a temperature
D.none of the above
第7题:
Ahave been
Bhave had
Chas been
Dare
第8题:
A、every cat is lucky
B、every dog has its day
C、every cat has its day
D、every dog is fortunate
第9题:
第10题:
()means that every project has a definite beginning and a definite end.
第11题:
Project phase
Unique
Temporary
Closure
第12题:
Projectphase
Unique
Temporary
Closure
第13题:
For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?
A project office memo
B project office directive
C project team meeting
D formal report
E counseling sessions
第14题:
112 Of the following, who has the ultimate responsibility for meeting project quality objectives?
A. Project Engineer
B. Project Manager
C. Functional Manager
D. Quality Assurance Manager
E. Project Owner
第15题:
182 The use of the project reports:
A. are not necessary on small projects
B. provides a means whereby various levels of authority can judge project performance
C. provides insight into project areas and the effectiveness of the control systems
D. All of the above
E. B and C
第16题:
96 A negative cost variance and positive schedule variance means:
A. The project is under budget and ahead of schedule
B. The project is over budget and behind schedule
C. The project is over budget and ahead of schedule
D. The project will be overrun but ahead of schedule at completion
第17题:
means that every project has a definite beginning and a definite end.
A.Project phase
B.Unique
C.Temporary
D.Closure
第18题:
●The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.(74) could provide the fund to cover the newly discovered work item.
(74) A. Contingency reserve
B. Project profit
C. Management reserve
D. Special fund
第19题:
A、have been
B、has been
C、have had
D、are
第20题:
Which of the following can best summarize the main idea of the passage?
A. With no Retriever, thousands of laptops are stolen every year.
B. A new software provides a means to reduce laptop theft.
C. Retriever has helped to find thieves and lost computers.
D. A new program offers a communication platform. with the thief.
第21题:
Every society has its own peculiar customs and()of acting.
第22题:
a liquid
a pressure
a temperature
none of the above
第23题:
all the 37 million people living in Spain are tourists
every year almost as many tourists visit Spain as there are people living in that country
every person living in Spain has to take care of a tourist
every Spanish is visited by a tourist every year
第24题:
all the 37 million people living in Spain are tourists
every year almost as many tourists visit Spain as there are people living in that country
every person living in Spain has to take care of a tourist
every Spaniard is visited by a tourist every year