    A negative cost variance and positive schedule variance means:

    A The project is under budget and ahead of schedule

    B The project is over budget and behind schedule

    C The project is over budget and ahead of schedule

    D The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第2题:

    40 For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?

    A. project office memo

    B. project office directive

    C. project team meeting

    D. formal report

    E.counseling sessions


    正确答案:D

  • 第3题:

    171 Documented work authorization provide:

    A. a means of effective internal coordination of the project's activities.

    B. an audit trail of all work authorized from project initiation to completion

    C.a means for communication of work activity between the project manager and the performing activities.

    D. All of the above

    E. A and B only


    正确答案:D

  • 第4题:

    78 Which of the following can the project manager use as a means of measuring project team effectiveness?

    A. Absenteeism

    B. Sponsor-approved salary increases

    C. Efficiency of the team

    D. Turnover of personnel

    E. Grievances


    正确答案:C

  • 第5题:

    ● The use of the project reports:

    A are not necessary on small projects

    B provides a means whereby various levels of authority can judge project performance

    C provides insight into project areas and the effectiveness of the control systems

    D All of the above

    E B and C


    正确答案:E

  • 第6题:

    Every liquid has a pressure at which it will vaporize and this pressure varies with temperatureThe word “which” means _____.

    A.a liquid

    B.a pressure

    C.a temperature

    D.none of the above


    正确答案:B

  • 第7题:

    Every means ____tried but with no end.

    Ahave been

    Bhave had

    Chas been

    Dare


    正确答案:C

  • 第8题:

    "i don't have money to fight him. these people are all the time in court, anyway." philip says. "but _______ and i have lots of patience,"

    A、every cat is lucky

    B、every dog has its day

    C、every cat has its day

    D、every dog is fortunate


    参考答案:B

  • 第9题:

    The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.

    A.Contingency reserve
    B.Project profit
    C.Management reserve
    D.Special fund

    答案:C
    解析:
    项目的预算还未最终确定,额外的工作已经发现,没有计划的预算或并不在项目范围内。管理储备可以提供该基金支付新发现的工作项。

  • 第10题:

    ()means that every project has a definite beginning and a definite end.

    • A、Project phase
    • B、Unique
    • C、Temporary
    • D、Closure

    正确答案:B

  • 第11题:

    单选题
    ()means that every project has a definite beginning and a definite end.
    A

    Project phase

    B

    Unique

    C

    Temporary

    D

    Closure


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    ()means that every project has a definite beginning and a definite end.
    A

    Projectphase

    B

    Unique

    C

    Temporary

    D

    Closure


    正确答案: A
    解析: 该题的关键词为"a definite beginning and a definite end",其语句结构为" (主语)means(谓语)that",含义为"什么意味着",该题干为项目管理的一个基本概念描述,描述了项目具备临时性特点。所以选择选项C。

  • 第13题:

    For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?

    A project office memo

    B project office directive

    C project team meeting

    D formal report

    E counseling sessions


    正确答案:D

  • 第14题:

    112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

    A. Project Engineer

    B. Project Manager

    C. Functional Manager

    D. Quality Assurance Manager

    E. Project Owner


    正确答案:B

  • 第15题:

    182 The use of the project reports:

    A. are not necessary on small projects

    B. provides a means whereby various levels of authority can judge project performance

    C. provides insight into project areas and the effectiveness of the control systems

    D. All of the above

    E. B and C


    正确答案:E

  • 第16题:

    96 A negative cost variance and positive schedule variance means:

    A. The project is under budget and ahead of schedule

    B. The project is over budget and behind schedule

    C. The project is over budget and ahead of schedule

    D. The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第17题:

    means that every project has a definite beginning and a definite end.

    A.Project phase

    B.Unique

    C.Temporary

    D.Closure


    正确答案:C
    解析:临时性是指每一个项目都有一个明确的开始时间和结束时间。

  • 第18题:

    ●The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.(74) could provide the fund to cover the newly discovered work item.

    (74) A. Contingency reserve

    B. Project profit

    C. Management reserve

    D. Special fund


    正确答案:C

  • 第19题:

    Every means () tried to help the two workers to catch up with others.

    A、have been

    B、has been

    C、have had

    D、are


    参考答案:B

  • 第20题:

    Which of the following can best summarize the main idea of the passage?

    A. With no Retriever, thousands of laptops are stolen every year.

    B. A new software provides a means to reduce laptop theft.

    C. Retriever has helped to find thieves and lost computers.

    D. A new program offers a communication platform. with the thief.


    正确答案:B

  • 第21题:

    Every society has its own peculiar customs and()of acting.

    • A、attitudes 
    • B、behavior
    • C、ways
    • D、means

    正确答案:C

  • 第22题:

    单选题
    Every liquid has a pressure at which it will vaporize and this pressure varies with temperatureThe word “which” means ().
    A

    a liquid

    B

    a pressure

    C

    a temperature

    D

    none of the above


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    The latter half of the last sentence in Paragraph 3, “or one tourist for every person living in Spain”, means _____.
    A

    all the 37 million people living in Spain are tourists

    B

    every year almost as many tourists visit Spain as there are people living in that country

    C

    every person living in Spain has to take care of a tourist

    D

    every Spanish is visited by a tourist every year


    正确答案: C
    解析:
    信息题。此句的意思是“每年有3700万游客来西班牙旅游,换句话说,每一个西班牙人就得接待一名游客。”

  • 第24题:

    单选题
    The latter half of the last sentence in Paragraph 3, i.e.,or one tourist for every person living in Spain means_______.
    A

    all the 37 million people living in Spain are tourists

    B

    every year almost as many tourists visit Spain as there are people living in that country

    C

    every person living in Spain has to take care of a tourist

    D

    every Spaniard is visited by a tourist every year


    正确答案: B
    解析: