Which phase and service component includes comparing the solution requirements with the bill of materials and high-level design in order to finalize the detailed business and technology requirements for the Cisco Unified Communications solution()A、Plan - 

题目

Which phase and service component includes comparing the solution requirements with the bill of materials and high-level design in order to finalize the detailed business and technology requirements for the Cisco Unified Communications solution()

  • A、Plan - Application Readiness Validation
  • B、Prepare - Proof of Concept
  • C、Prepare - Technology Strategy Development
  • D、Plan - Systems Requirements Validation

相似考题
更多“Which phase and̳”相关问题
  • 第1题:

    141 Feasibility studies occur in which life cycle phase (s)?

    A. Conceptual

    B. Conceptual or Development

    C. Execution

    D. Preliminary planning

    E. any life cycle phase


    正确答案:A

  • 第2题:

    88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B. Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第3题:

    ● Feasibility studies occur in which life cycle phase (s)?

    A Conceptual

    B Conceptual or Development

    C Execution

    D Preliminary planning

    E any life cycle phase


    正确答案:A

  • 第4题:

    In which phase of the software engineering process is the Software Requirements Specification developed?

    A. definition phase

    B.engineering

    C.maintenance

    D.development phase


    正确答案:A

  • 第5题:

    During which phase is a proposal developed and delivered? ()

    A.Prepare

    B.Plan

    C.Design

    D.Operate


    参考答案:A

  • 第6题:

    The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.

    A.system charter
    B.system scope definition
    C.system blueprint
    D.system requirements document

    答案:B
    解析:
    翻译:系统分析阶段的目的是建立新系统的逻辑模型,第一步就是进行(71),调查业务流程并记录新系统必须做哪些以满足用户需求。这一步是(72)的延续,可以使用调查结果构建业务模型,数据和流程模型以及对象模型。系统分析阶段的可交付成果是(73),它描述了管理和用户要求,成本和收益,还有可替代的方案。系统设计阶段的目的是创建一个能够满足系统所有需求文件要求的物理模型。 在系统设计阶段,需要确定(74),程序员通过系统过程模型把逻辑设计转换为程序模块和代码。该阶段的可交付成果是(75),提交给管理层和用户审查和批准。(73) A.系统章程B.系统范围定义C.系统蓝图 D.系统需求文件
    参考答案:(73)B

  • 第7题:

    Which of the following options lists the steps in PPP session establishment in the correct order?()

    • A、Optional authentication phase, link establishment phase, network layer protocol phase.
    • B、Network layer protocol phase, link establishment phase, optional authentication phase.
    • C、Network layer protocol phase, optional authentication phase, link establishment phase.
    • D、Link establishment phase, network layer protocol phase, optional authentication phase.
    • E、Link establishment phase, optional authentication phase, network layer protocol phase.
    • F、Optional authentication phase, network layer protocol phase, link establishment phase.

    正确答案:E

  • 第8题:

    During which phase of the boot process is the rootvg volume group varied on and the root file system (hd4) checked?()  

    • A、Boot phase 1
    • B、Boot phase 2
    • C、Boot phase 3
    • D、Boot phase 4

    正确答案:B

  • 第9题:

    In which phase should a TDA be performed of the following?()

    • A、Server deployment
    • B、Installation and server configuration
    • C、Problem determination / resolution
    • D、Needs analysis and design

    正确答案:D

  • 第10题:

    单选题
    Phase I and Phase II DMVPN differ in terms of which of these characteristics?()
    A

    Utilization of spoke-to-spoke dynamic tunnels

    B

    Utilization of multipoint GRE tunnels at the hub site

    C

    Utilization of hub-to-spoke dynamic tunnels

    D

    Support for multicast


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    Select the wireless service component in the implement phase in which operations responsibilities are defined and transferred to the operate phase team.()
    A

    Ongoing Support Handoff Meeting

    B

    Staff Training

    C

    Detailed Design Development

    D

    Staging and System Migration


    正确答案: A
    解析: 暂无解析

  • 第12题:

    多选题
    Which two statements are true about CAC?()
    A

    CAC is implemented in the call setup phase to allocate bandwidth resources

    B

    CAC is implemented in the call maintenance phase to allocate bandwidth resources

    C

    CAC is utilized during the call teardown phase to ensure that all resources have been released

    D

    CAC uses the Cisco RSVP (Resource Reservation Protocol) Agent to integrate call-processing capabilities with the underlying network infrastructure

    E

    CAC is implemented in the call setup phase to determine the destination of the call


    正确答案: B,E
    解析: 暂无解析

  • 第13题:

    6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第14题:

    82 Which of the following are included in the Acquisition phase(s) of the project life cycle.

    A. concept and development

    B. development and planning

    C. execution and phase-out

    D. planning and implementation

    E. concept and planning


    正确答案:C

  • 第15题:

    ●In which phase of the software engineering process is the Software Requirements Specification developed? (68) .

    (68) A.development phase

    B.engineering phase

    C.maintenance phase

    D.Definition phase


    正确答案:D
    【解析】软件需求说明在软件开发的哪个周期阶段出来?

  • 第16题:

    Which phase of the software development requires the most development time?

    A.the design phase

    B.the testing phase

    C.the maintenance phase

    D.the development phase


    正确答案:C

  • 第17题:

    Which of the following statements is correct?

    A.The definition phase results in the Software Requirements Specification.

    B.Testing is optional in software life cycle.

    C.CASE tools can only aid in the design phase of a software life cycle.

    D.A change during a later phase does not require the documentation of all earlier phases to be updated.


    正确答案:A

  • 第18题:

    The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.

    A.systems planning phase
    B.systems modeling phase
    C.systems analysis phase
    D.systems design phase

    答案:A
    解析:
    翻译:系统分析阶段的目的是建立新系统的逻辑模型,第一步就是进行(71),调查业务流程并记录新系统必须做哪些以满足用户需求。这一步是(72)的延续,可以使用调查结果构建业务模型,数据和流程模型以及对象模型。系统分析阶段的可交付成果是(73),它描述了管理和用户要求,成本和收益,还有可替代的方案。系统设计阶段的目的是创建一个能够满足系统所有需求文件要求的物理模型。 在系统设计阶段,需要确定(74),程序员通过系统过程模型把逻辑设计转换为程序模块和代码。该阶段的可交付成果是(75),提交给管理层和用户审查和批准。(72) A.系统计划阶段B.系统建模阶段C.系统分析阶段 D.系统设计阶段
    参考答案:(72)A

  • 第19题:

    Which of the following is NOT a phase of the troubleshooting process?()

    • A、confirm the repair
    • B、define the problem
    • C、document the results
    • D、simplify the problem

    正确答案:D

  • 第20题:

    During which boot phase is the rootvg first activated()

    • A、Phase 1
    • B、Phase 2
    • C、Phase 3
    • D、POST Phase

    正确答案:B

  • 第21题:

    单选题
    Which of the following options lists the steps in PPP session establishment in the correct order?()
    A

    Optional authentication phase, link establishment phase, network layer protocol phase.

    B

    Network layer protocol phase, link establishment phase, optional authentication phase.

    C

    Network layer protocol phase, optional authentication phase, link establishment phase.

    D

    Link establishment phase, network layer protocol phase, optional authentication phase.

    E

    Link establishment phase, optional authentication phase, network layer protocol phase.

    F

    Optional authentication phase, network layer protocol phase, link establishment phase.


    正确答案: E
    解析: 暂无解析

  • 第22题:

    单选题
    In which phase is a systems acceptance test plan developed and documented?()
    A

    Implement

    B

    Design

    C

    Prepare

    D

    Operate


    正确答案: A
    解析: 暂无解析

  • 第23题:

    多选题
    Which three service components belong to the operate phase()
    A

    Change Management

    B

    Operations Implementation

    C

    System monitoring

    D

    Incident Management

    E

    Operations Assessment


    正确答案: D,E
    解析: 暂无解析

  • 第24题:

    单选题
    During which phase is a proposal developed and delivered?()
    A

    Prepare

    B

    Plan

    C

    Design

    D

    Operate


    正确答案: B