更多““ESTIMATED ARRIVAL TIME”的中文是“实际到达时间”。”相关问题
  • 第1题:

    Where a charter-party specifies the estimated time of arrival of a vessel at the port of loading, there is ________ on the shipowners to sail to there on the date on which when proceeding with all convenient speed it would normally reach the port on or about the estimated date of arrival.

    A.a necessary right

    B.an absolute observation

    C.an absolute obligation

    D.a possible solution


    正确答案:C

  • 第2题:

    The path that a vessel is expected to follow,represented on a chart by a line drawn from the point of departure to the point of arrival,is the ______.

    A.DR plot

    B.track line

    C.heading

    D.estimated course


    正确答案:B

  • 第3题:

    汉译英:“装货港;到达日期”,正确的翻译为:( )。
    A. Port of loading ; Date of departure B. Port of discharge ; Date of departure
    C. Port of loading ; Date of arrival D. Port of discharge ; Date of arrival


    答案:C
    解析:

  • 第4题:

    Which of these terms refers to call issues that cause variations in timing or time of arrival?()

    • A、queuing
    • B、jitter
    • C、packet loss
    • D、digitized sampling
    • E、signal-to-noise ratio ratio

    正确答案:B

  • 第5题:

    在雷达避碰中,DCPA的中文意思是()

    • A、到达最接近点时间
    • B、最近会遇距离
    • C、最小会遇时间
    • D、所有选项都不对

    正确答案:B

  • 第6题:

    中式英语“long time no see”译成中文是哪句常用语?


    正确答案:好久不见

  • 第7题:

    到达列车填写列车实际接入停车时间,始发列车填写()时间。

    • A、列车实际停车
    • B、车列实际编完
    • C、列车实际编完
    • D、车列实际停车

    正确答案:B

  • 第8题:

    Jitter is an unwanted variation of one or more characteristics of a periodic signal in electronics and telecommunications and()refers to call issues that cause variations in timing or time of arrival.

    • A、echo
    • B、jitter
    • C、packet loss
    • D、digitized sampling

    正确答案:B

  • 第9题:

    单选题
    The tallying of cargo refers to such kind of work that the amount and condition of all cargo should be checked().
    A

    after its arrival at the destination

    B

    during the ship's voyage at sea

    C

    before they come to the dock

    D

    during the time when the loading or diacharging is going on


    正确答案: C
    解析: 暂无解析

  • 第10题:

    问答题
    翻译:DTA definite time of arrival

    正确答案: 船舶确切到港时间
    解析: 暂无解析

  • 第11题:

    问答题
    翻译:ETA estimated time of arrival

    正确答案: 预计到达时间
    解析: 暂无解析

  • 第12题:

    单选题
    Jitter is an unwanted variation of one or more characteristics of a periodic signal in electronics and telecommunications and()refers to call issues that cause variations in timing or time of arrival.
    A

     echo

    B

     jitter

    C

     packet loss

    D

     digitized sampling


    正确答案: B
    解析: 暂无解析

  • 第13题:

    A position that is obtained by using two or more intersecting lines of position taken at nearly the same time,is a(n) ______.

    A.fix

    B.running fix

    C.estimated position

    D.dead-reckoning position


    正确答案:A

  • 第14题:

    汉译英:“装货港;到达日期”,正确的翻译为:()
    A.Port of loading ; Date of departure
    B.Port of discharge ; Date of departure
    C.Port of loading ; Date of arrival
    D.Port of discharge ; Date of arrival


    答案:C
    解析:

  • 第15题:

    一旦数据到达,将首先触发Winsock控件的()。

    AData Arrival事件

    BConnection Request事件

    CData Send事件

    DData Get事件


    A

  • 第16题:

    翻译:ETA estimated time of arrival


    正确答案:预计到达时间

  • 第17题:

    翻译:DTA definite time of arrival


    正确答案:船舶确切到港时间

  • 第18题:

    一旦数据到达,将首先触发Winsock控件的()。

    • A、Data Arrival事件
    • B、Connection Request事件
    • C、Data Send事件
    • D、Data Get事件

    正确答案:A

  • 第19题:

    Can you deliver my present at the time I want?译成中文是()?


    正确答案:你们可以按我指定的时间把礼物送到吗?

  • 第20题:

    在FPL电报中,estimated off-block time指的是()

    • A、自飞机开始滑跑的时间
    • B、飞机的撤轮档开始进行与起飞活动有关预计时间
    • C、飞机预计起飞的时间
    • D、飞机在空中的总预计经过时间

    正确答案:B

  • 第21题:

    单选题
    Which of these terms refers to call issues that cause variations in timing or time of arrival?()
    A

    queuing

    B

    jitter

    C

    packet loss

    D

    digitized sampling

    E

    signal-to-noise ratio ratio


    正确答案: D
    解析: 暂无解析

  • 第22题:

    单选题
    It is apparent that there was not sufficient depth of water()and I claim that the estimated arrival draft as radioed to the agent to report to you was a close one.
    A

    for my vessel crossing safely

    B

    my vessel is to cross safely

    C

    for my vessel to cross safely

    D

    for my vessel's crossing safely


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    Where a charter-party specifies the estimated time of arrival of a vessel at the port of loading,there is()obligation on the shipowners to sail to there on the date on which when proceeding with all convenient speed it would normally reach the port on or about the estimated date of arrival.
    A

    an optional

    B

    a reasonable

    C

    an absolute

    D

    rational


    正确答案: A
    解析: 暂无解析