2 The risk committee at Southern Continents Company (SCC) met to discuss a report by its risk manager, StephanieField. The report focused on a number of risks that applied to a chemicals factory recently acquired by SCC in anothercountry, Southland. She e

题目

2 The risk committee at Southern Continents Company (SCC) met to discuss a report by its risk manager, Stephanie

Field. The report focused on a number of risks that applied to a chemicals factory recently acquired by SCC in another

country, Southland. She explained that the new risks related to the security of the factory in Southland in respect of

burglary, to the supply of one of the key raw materials that experienced fluctuations in world supply and also an

environmental risk. The environmental risk, Stephanie explained, was to do with the possibility of poisonous

emissions from the Southland factory.

The SCC chief executive, Choo Wang, who chaired the risk committee, said that the Southland factory was important

to him for two reasons. First, he said it was strategically important to the company. Second, it was important because

his own bonuses depended upon it. He said that because he had personally negotiated the purchase of the Southland

factory, the remunerations committee had included a performance bonus on his salary based on the success of the

Southland investment. He told Stephanie that a performance-related bonus was payable when and if the factory

achieved a certain level of output that Choo considered to be ambitious. ‘I don’t get any bonus at all until we reach

a high level of output from the factory,’ he said. ‘So I don’t care what the risks are, we will have to manage them.’

Stephanie explained that one of her main concerns arose because the employees at the factory in Southland were not

aware of the importance of risk management to SCC. She said that the former owner of the factory paid less attention

to risk issues and so the staff were not as aware of risk as Stephanie would like them to be. ‘I would like to get risk

awareness embedded in the culture at the Southland factory,’ she said.

Choo Wang said that he knew from Stephanie’s report what the risks were, but that he wanted somebody to explain

to him what strategies SCC could use to manage the risks.

Required:

(a) Describe four strategies that can be used to manage risk and identify, with reasons, an appropriate strategy

for each of the three risks mentioned in the case. (12 marks)


相似考题
参考答案和解析
正确答案:
(a) Risks at Southland and management strategies
Risk management strategies
There are four strategies for managing risk and these can be undertaken in sequence. In the first instance, the organisation
should ask whether the risk, once recognised, can be transferred or avoided.
Transference means passing the risk on to another party which, in practice means an insurer or a business partner in another
part of the supply chain (such as a supplier or a customer).
Avoidance means asking whether or not the organisation needs to engage in the activity or area in which the risk is incurred.
If it is decided that the risk cannot be transferred nor avoided, it might be asked whether or not something can be done to
reduce or mitigate the risk. This might mean, for example, reducing the expected return in order to diversify the risk or
re-engineer a process to bring about the reduction.
Risk sharing involves finding a party that is willing to enter into a partnership so that the risks of a venture might be spread
between the two parties. For example an investor might be found to provide partial funding for an overseas investment in
exchange for a share of the returns.
Finally, an organisation might accept or retain the risk, believing there to be no other feasible option. Such retention should
be accepted when the risk characteristics are clearly known (the possible hazard, the probability of the risk materialising and
the return expected as a consequence of bearing the risk).
Risks in the case and strategy
There are three risks to the Southland factory described in the case.
Risk to the security of the factory in Southland. This risk could be transferred. The transference of this risk would be through
insurance where an insurance company will assume the potential liability on payment, by SCC, of an appropriate insurance
premium.
Risk to the supply of one of the key raw materials that experienced fluctuations in world supply. This risk will probably have
to be accepted although it may be possible, with redesigning processes, to reduce the risk.
If the raw material is strategically important (i.e. its use cannot be substituted or reduced), risk acceptance will be the only
possible strategy. If products or process can be redesigned to substitute or replace its use in the factory, the supply risk can
be reduced.
The environmental risk that concerned a possibility of a poisonous emission can be reduced by appropriate environmental
controls in the factory. This may require some process changes such as inventory storage or amendments to internal systems
to ensure that the sources of emissions can be carefully monitored.
Tutorial note: the strategies for the individual risks identified in the case are not the only appropriate responses and other
strategies are equally valid providing they are supported with adequate explanation.
更多“2 The risk committee at Southern Continents Company (SCC) met to discuss a report by its risk manager, StephanieField. The report focused on a number of risks that applied to a chemicals factory recently acquired by SCC in anothercountry, Southland. She e”相关问题
  • 第1题:

    144 Risk event probability is defined as:

    A. the total number of possible events divided into the expectations or frequency of the risk event

    B. the number of times the risk event may occur

    C. the fraction of the total project tasks which may be affected by the risk event

    D. the total number of possible events divided into the consequences of the risk event.

    E. A and B


    正确答案:A

  • 第2题:

    John Pentanol was appointed as risk manager at H&Z Company a year ago and he decided that his first task was to examine the risks that faced the company. He concluded that the company faced three major risks, which he assessed by examining the impact that would occur if the risk were to materialise. He assessed Risk 1 as being of low potential impact as even if it materialised it would have little effect on the company’s strategy. Risk 2 was assessed as being of medium potential impact whilst a third risk, Risk 3, was assessed as being of very high potential impact.

    When John realised the potential impact of Risk 3 materialising, he issued urgent advice to the board to withdraw from the activity that gave rise to Risk 3 being incurred. In the advice he said that the impact of Risk 3 was potentially enormous and it would be irresponsible for H&Z to continue to bear that risk.

    The company commercial director, Jane Xylene, said that John Pentanol and his job at H&Z were unnecessary and that risk management was ‘very expensive for the benefits achieved’. She said that all risk managers do is to tell people what can’t be done and that they are pessimists by nature. She said she wanted to see entrepreneurial risk takers in H&Z and not risk managers who, she believed, tended to discourage enterprise.

    John replied that it was his job to eliminate all of the highest risks at H&Z Company. He said that all risk was bad and needed to be eliminated if possible. If it couldn’t be eliminated, he said that it should be minimised.

    (a) The risk manager has an important role to play in an organisation’s risk management.

    Required:

    (i) Describe the roles of a risk manager. (4 marks)

    (ii) Assess John Pentanol’s understanding of his role. (4 marks)

    (b) With reference to a risk assessment framework as appropriate, criticise John’s advice that H&Z should

    withdraw from the activity that incurs Risk 3. (6 marks)

    (c) Jane Xylene expressed a particular view about the value of risk management in H&Z Company. She also said that she wanted to see ‘entrepreneurial risk takers’.

    Required:

    (i) Define ‘entrepreneurial risk’ and explain why it is important to accept entrepreneurial risk in business

    organisations; (4 marks)

    (ii) Critically evaluate Jane Xylene’s view of risk management. (7 marks)


    正确答案:

    (a) (i) Roles of a risk manager
    Providing overall leadership, vision and direction, involving the establishment of risk management (RM) policies,
    establishing RM systems etc. Seeking opportunities for improvement or tightening of systems.
    Developing and promoting RM competences, systems, culture, procedures, protocols and patterns of behaviour. It is
    important to understand that risk management is as much about instituting and embedding risk systems as much as
    issuing written procedure. The systems must be capable of accurate risk assessment which seem not to be the case at
    H&Z as he didn’t account for variables other than impact/hazard.
    Reporting on the above to management and risk committee as appropriate. Reporting information should be in a form
    able to be used for the generation of external reporting as necessary. John’s issuing of ‘advice’ will usually be less useful
    than full reporting information containing all of the information necessary for management to decide on risk policy.

    Ensuring compliance with relevant codes, regulations, statutes, etc. This may be at national level (e.g. Sarbanes Oxley)
    or it may be industry specific. Banks, oil, mining and some parts of the tourism industry, for example, all have internal
    risk rules that risk managers are required to comply with.
    [Tutorial note: do not reward bullet lists. Study texts both use lists but question says ‘describe’.]
    (ii) John Pentanol’s understanding of his role
    John appears to misunderstand the role of a risk manager in four ways.
    Whereas the establishment of RM policies is usually the most important first step in risk management, John launched
    straight into detailed risk assessments (as he saw it). It is much more important, initially, to gain an understanding of
    the business, its strategies, controls and risk exposures. The assessment comes once the policy has been put in place.
    It is important for the risk manager to report fully on the risks in the organisation and John’s issuing of ‘advice’ will usually
    be less useful than full reporting information. Full reporting would contain all of the information necessary for
    management to decide on risk policy.
    He told Jane Xylene that his role as risk manager involved eliminating ‘all of the highest risks at H&Z Company’ which
    is an incorrect view. Jane Xylene was correct to say that entrepreneurial risk was important, for example.
    The risk manager is an operational role in a company such as H&Z Company and it will usually be up to senior
    management to decide on important matters such as withdrawal from risky activities. John was being presumptuous
    and overstepping his role in issuing advice on withdrawal from Risk 3. It is his job to report on risks to senior
    management and for them to make such decisions based on the information he provides.

    (b) Criticise John’s advice
    The advice is based on an incomplete and flawed risk assessment. Most simple risk assessment frameworks comprise at least
    two variables of which impact or hazard is only one. The other key variable is probability. Risk impact has to be weighed
    against probability and the fact that a risk has a high potential impact does not mean the risk should be avoided as long as
    the probability is within acceptable limits. It is the weighted combination of hazard/impact and probability that forms the basis
    for meaningful risk assessment.
    John appears to be very certain of his impact assessments but the case does not tell us on what information the assessment
    is made. It is important to recognise that ‘hard’ data is very difficult to obtain on both impact and probability. Both measures
    are often made with a degree of assumption and absolute measures such as John’s ranking of Risks 1, 2 and 3 are not as
    straightforward as he suggests.
    John also overlooks a key strategic reason for H&Z bearing the risks in the first place, which is the return achievable by the
    bearing of risk. Every investment and business strategy carries a degree of risk and this must be weighed against the financial
    return that can be expected by the bearing of the risk.
    (c) (i) Define ‘entrepreneurial risk’
    Entrepreneurial risk is the necessary risk associated with any new business venture or opportunity. It is most clearly seen
    in entrepreneurial business activity, hence its name. In ‘Ansoff’ terms, entrepreneurial risk is expressed in terms of the
    unknowns of the market/customer reception of a new venture or of product uncertainties, for example product design,
    construction, etc. There is also entrepreneurial risk in uncertainties concerning the competences and skills of the
    entrepreneurs themselves.
    Entrepreneurial risk is necessary, as Jane Xylene suggested, because it is from taking these risks that business
    opportunities arise. The fact that the opportunity may not be as hoped does not mean it should not be pursued. Any
    new product, new market development or new activity is a potential source of entrepreneurial risk but these are also the
    sources of future revenue streams and hence growth in company value.

    (ii) Critically evaluate Jane Xylene’s view of risk management
    There are a number of arguments against risk management in general. These arguments apply against the totality of risk
    management and also of the employment of inappropriate risk measures.
    There is a cost associated with all elements of risk management which must obviously be borne by the company.
    Disruption to normal organisational practices and procedures as risk systems are complied with.
    Slowing (introducing friction to) the seizing of new business opportunities or the development of internal systems as they
    are scrutinised for risk.
    ‘STOP’ errors can occur as a result of risk management systems where a practice or opportunity has been stopped on
    the grounds of its risk when it should have been allowed to proceed. This may be the case with Risk 3 in the case.
    (Contrast with ‘GO’ errors which are the opposite of STOP errors.)
    There are also arguments for risk management people and systems in H&Z. The most obvious benefit is that an effective
    risk system identifies those risks that could detract from the achievements of the company’s strategic objectives. In this
    respect, it can prevent costly mistakes by advising against those actions that may lose the company value. It also has
    the effect of reassuring investors and capital markets that the company is aware of and is in the process of managing
    its risks. Where relevant, risk management is necessary for compliance with codes, listing rules or statutory instruments.

  • 第3题:

    Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses


    正确答案:A
    风险管理并不能使得项目经理及其团队在项目的规划过程中避免大多数的风险。

  • 第4题:

    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control


    正确答案:B
    定量风险分析过程分析风险事件的影响并对这些影响赋予一个数值化的评价。

  • 第5题:

    The new secretary is supposed to report to the manager as soon as she ().

    A、is going to arrive

    B、is arriving

    C、arrives

    D、will arrive


    参考答案:C

  • 第6题:

    ()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.

    A.Identity risks

    B.Control risks

    C.Plan risk responses

    D.Plan risk management


    正确答案:B

  • 第7题:

    The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control


    正确答案:B
    解析:定量风险分析过程分析风险事件的影响并对这些风险赋予一个数值化的评价。

  • 第8题:

    共用题干
    Cigars Instead?
    Smoking one or two cigars a day doubles the risk of cancers of the lip,tongue,mouth,and throat,according to a government study.
    Daily cigars also increase the risk of lung cancer and cancer of the esophagus,and increase the risk of cancer of the larynx(voice box)sixfold,say researchers at the National Cancer Institu- te in Bethesda,Maryland.
    In addition,the report revealed that smoking three or four cigars a day increased the risk of oral cancer to 8.5 times the risk for nonsmokers and the risk of esophageal cancer by four times the risk of nonsmokers.
    The health effects of smoking cigars is one of eight sections of the article"Cigars:Health
    Effects and Trends".The researchers report that,compared with a cigarette,a large cigar emits up to 90 times as much carcinogenic tobacco-specific nitrosamines.
    "This article provides clear and invaluable information about the disturbing increase in cigar use and the significant public health consequences for the country,"said Dr. Richard Klausner, director of the National Cancer Institute,in a statement.
    "The data are clear-the harmful substances and carcinogens in cigar smoke,like cigarettes,are associated with the increased risks of several kinds of cancers as well as heart and lung diseases,"he added."In other words,cigars are not safe alternatives to cigarettes and may be addictive."
    "To those individuals who may be thinking about smoking cigars,our advice is-don't. To those currently smoking cigars,quitting is the only way to eliminate completely the cancer,heart and lung disease risks,"warned Klausner.
    According to a National Cancer Institute press release,there haven't been any studies on the health effects on nonsmokers at cigar social events,but“... a significant body of evidence clearly demonstrates an increased lung cancer risk from secondhand smoke."

    According to the report,smoking three or four cigars a day______.
    A: increases the risk of oral cancer for non-smokers
    B: greatly increases the risk of oral cancer for smokers
    C: increases the risk of more than one cancer for non-smokers.
    D: greatly increases the risk of more than one cancer for smokers

    答案:D
    解析:
    第三段中“smoking three or four cigars a day increased the risk of oral cancer to 8. 5 times the risk for nonsmokers and the risk of esophageal cancer by four times the risk of non-smokers.”谈论了吸烟者患癌症的可能性(与不吸烟者相比分别增加到8. 5倍和4倍)。


    第一段中提到lip , tongue , mouth , throat四种,第二段中提到lung, esophagus, larynx 三种,共七种,第三段中的oral是对lip , tongue , mouth等的统称,不应再算做一种。


    倒数第三段中的一句话概括了文章的中心,即“...cigars are not safe alternatives to cigarettes and may be addictive."


    倒数第二段中医生的建议是“To those currently smoking cigars , quitting is the only way to eliminate completely the cancer...",即完全放弃。


    二手吸烟,即我们所说的被动吸烟,最后一段中的“nonsmokers at cigar social events" 提示了这一情景。

  • 第9题:

    setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this?()

    • A、risk avoidance
    • B、risk acceptance
    • C、risk mitigation
    • D、contingency plan

    正确答案:C

  • 第10题:

    ()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.

    • A、Quantitative Risk Analysis
    • B、Qualitative Risk Analysis
    • C、Enterprise Environmental Factors
    • D、Risk Management Plan

    正确答案:B

  • 第11题:

    The general additional risks including()are covered in all risks coverage.

    • A、risk of shortage
    • B、risk of leakage
    • C、strikes risk
    • D、risk of rust

    正确答案:A,B,D

  • 第12题:

    单选题
    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.
    A

    Riskldentification

    B

    Quantitative Risk Analysis

    C

    Qualitative Risk Analysis

    D

    Risk Monitoring and Control


    正确答案: C
    解析: 该题的关键词为"ascertains、documenting the risks' characteristics",其语句结构为"The()_process(主语)ascertains(谓语)which risks have the potential of affecting the project and documenting the risks' characteristics",含义为"什么过程确定那些可能影响项目的风险并记录这些风险特征",根据风险管理知识领域,识别并记录风险是风险识别子过程的主要任务,所以选择A

  • 第13题:

    2 Chen Products produces four manufactured products: Products 1, 2, 3 and 4. The company’s risk committee recently

    met to discuss how the company might respond to a number of problems that have arisen with Product 2. After a

    number of incidents in which Product 2 had failed whilst being used by customers, Chen Products had been presented

    with compensation claims from customers injured and inconvenienced by the product failure. It was decided that the

    risk committee should meet to discuss the options.

    When the discussion of Product 2 began, committee chairman Anne Ricardo reminded her colleagues that, apart from

    the compensation claims, Product 2 was a highly profitable product.

    Chen’s risk management committee comprised four non-executive directors who each had different backgrounds and

    areas of expertise. None of them had direct experience of Chen’s industry or products. It was noted that it was

    common for them to disagree among themselves as to how risks should be managed and that in some situations,

    each member proposed a quite different strategy to manage a given risk. This was the case when they discussed

    which risk management strategy to adopt with regard to Product 2.

    Required:

    (a) Describe the typical roles of a risk management committee. (6 marks)


    正确答案:
    (a) Typical roles of a risk management committee
    The typical roles of a risk management committee are as follows:
    To agree and approve the risk management strategy and policies. The design of risk policy will take into account the
    environment, the strategic posture towards risk, the product type and a range of other relevant factors.
    Receiving and reviewing risk reports from affected departments. Some departments will file regular reports on key risks (such
    as liquidity assessments from the accounting department, legal risks from the company secretariat or product risks from the
    sales manager).
    Monitoring overall exposure and specific risks. If the risk policy places limits on the total risk exposure for a given risk then
    this role ensures that limits are adhered to. In the case of certain strategic risks, monitoring could occur on a very frequent
    basis whereas for more operational risks, monitoring will more typically occur to coincide with risk management committee
    meetings.
    Assessing the effectiveness of risk management systems. This involves getting feedback from departments and the internal
    audit function on the workings of current management and risk mitigation systems.
    Providing general and explicit guidance to the main board on emerging risks and to report on existing risks. This will involve
    preparing reports on apparent risks and assessing their probability of being realised and their potential impact if they do.
    To work with the audit committee on designing and monitoring internal controls for the management and mitigation of risks.
    If the risk committee is part of the executive structure, it will likely have an advisory role in respect of its input into the audit
    committee. If it is non-executive, its input may be more directly influential.
    [Tutorial note: other roles may be suggested that, if relevant, will be rewarded]

  • 第14题:

    (b) (i) Discuss the relationship between the concepts of ‘business risk’ and ‘financial statement risk’; and

    (4 marks)


    正确答案:
    (b) (i) Business risk is defined as a threat which could mean that a business fails to meet an ongoing business objective.
    Business risks represent problems which are faced by the management of a business, and these problems should be
    identified and assessed for their possible impact on the business.
    Financial statement risk is the risk that components of the financial statements could be misstated, through inaccurate
    or incomplete recording of transactions or disclosure. Financial statement risks therefore represent potential errors or
    deliberate misstatements in the published accounts of a business.
    There is usually a direct relationship between business risk and financial statement risk. Generally a business risk, if not
    addressed by management, will have an impact on specific components of the financial statements. For example, for
    Medix Co, declining demand for metal surgical equipment has been identified as a business risk. An associated financial
    statement risk is the potential over-valuation of obsolete inventory.
    Sometimes business risks have a more general effect on the financial statements. Weak internal systems and controls
    are often identified as a business risk. Inadequacies in systems and controls could lead to errors or misstatements in
    any area of the financial statements so auditors would perceive this as a general audit risk factor.
    Business risks are often linked to going concern issues, because if a business is failing to meet objectives such as cash
    generation, or revenue maximisation, then it may struggle to continue in operational existence. In terms of financial
    statement risk, going concern is a very specific issue, and the risk is normally the inadequate disclosure of going concern
    problems. In the extreme situation where a business is definitely not a going concern, then the risk is that the financial
    statements have been prepared on the wrong basis, as in this case the ‘break up basis’ should be used.
    Business risk and financial statement risk concepts can both be used by auditors in order to identify areas of the financial
    statements likely to be misstated at the year end. The business risk approach places the auditor ‘in the shoes’ of
    management, and therefore provides deeper insight into the operations of the business and generates extensive business
    understanding.

  • 第15题:

    The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


    正确答案:A
    风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

  • 第16题:

    Banks in international lending face the risks common to all banks: liquidity risk, interest rate risk, credit (asset) risk, and contingent liabilities risk.

    A.Right

    B.Wrong

    C.Doesn't say


    正确答案:C
    解析:文章通篇提及银行面临的三类风险,并加以举例,并没有提及Banks in international lending。

  • 第17题:

    setting redundant components in subsystem to handle with the risks brought by the defaultsof original components,what kind of risk response strategy is this?()

    A.risk avoidance

    B.risk acceptance

    C.risk mitigation

    D.contingency plan


    正确答案:C
    设置冗余组件的子系统处理的原始成分的违约带来的风险,这是一种什么样的风险应对策略?()A、风险规避B、风险接受C、风险减轻D、应急计划

  • 第18题:

    The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control


    正确答案:A
    解析:项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。选项A是风险识别,选项B是定量风险分析,选项C是定性风险分析,选项D是风险监控。

  • 第19题:

    Workers maintain that the company's __________to implement modern safety regulations puts everyone in the factory at risk of injury.

    A.discouragement
    B.indecision
    C.unwillingness
    D.hindrance

    答案:C
    解析:
    “that”从句的主语部分表示“公司不愿意实行最新的安全规则”,因此C为正确答案。

  • 第20题:

    The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    A.Risk Identification
    B.Quantitative Risk Analysis
    C.Qualitative Risk Analysis
    D.Risk Monitoring anD.Control

    答案:A
    解析:
    项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。
    A.风险识别 B.定量风险分析 C.定性风险分析 D.风险检测与控制

  • 第21题:

    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    • A、Riskldentification
    • B、Quantitative Risk Analysis
    • C、Qualitative Risk Analysis
    • D、Risk Monitoring and Control

    正确答案:A

  • 第22题:

    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

    • A、Risk Identification
    • B、Quantitative Risk Analysis
    • C、Qualitative Risk Analysis
    • D、Risk Monitoring and Control

    正确答案:B

  • 第23题:

    单选题
    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
    A

    Risk Identification

    B

    Quantitative Risk Analysis

    C

    Qualitative Risk Analysis

    D

    Risk Monitoring and Control


    正确答案: C
    解析: 暂无解析